Fernbrook Jerry Green
Status: Complete
Efficient Warehousing Solutions: The Fernbrook Jerry Green Project
At George Grant Engineering Ltd. (GGE), we take pride in delivering high-quality structural steel solutions that meet the unique needs of each project. One of our notable achievements is the Fernbrook Jerry Green project in Wiri, completed in collaboration with Haydn & Rollett.
Tasked with constructing two large warehouses, our team overcame significant challenges, including material supply delays caused by the Covid-19 pandemic. By accelerating the installation program, we ensured that the project was completed within the agreed time frame, demonstrating our commitment to delivering on our promises despite external pressures.
Project Overview:
• Client: Haydn & Rollett
• Scope: Fabrication and erection of two large warehouses
• Project Weight: 938 tonnes
• Duration: 5 months
• Year of Completion: 2022
• Site Challenges: Material supply delays due to Covid-19